Summary

Continuous energy monitoring across logistics operation centres drives lighting, heating and cooling upgrades that cut electricity and natural gas consumption.

Context

Submitted through the COP31 Sustainable Transformation Awards · SKD Türkiye (WBCSD Global Network Partner)

Trendyol is an e-commerce company that runs a network of operation centres supporting one of the largest logistics networks in Türkiye.

Operation centres consume energy continuously. Lighting covers large floor areas for most of the day, heating, ventilation and air conditioning systems condition high-volume spaces, and heating and hot water loads continue through the year. As order volume grows, that consumption and the emissions attached to it grow with it.

Energy efficiency in the sector is often handled as a series of isolated technical upgrades at individual sites and reported once. That produces a saving where it was applied and no mechanism for repeating it anywhere else.

The adopting company's approach is to manage energy as an operational performance area instead. Consumption is monitored through building management systems and meter readings, improvement opportunities are identified from that data, investments are prioritised by payback and carbon reduction potential, and proven measures are standardised and transferred to other centres.

The consolidated programme was established in 2026, bringing together energy efficiency initiatives implemented across Trendyol's operation centres, and sits inside the climate commitments announced in 2022, under which the company targets net zero for emissions from its own operations by 2040 and for value chain emissions by 2050. Energy and emissions performance is reported through the company's sustainability disclosures (1).

Location of the initiative: Operation centres in Türkiye


Solution

The model has two halves: a measurement layer that runs continuously, and a portfolio of physical measures that the measurement layer selects and then verifies.

The measurement layer draws electricity and natural gas consumption from building management systems, meter readings and facility-level operational performance records. Data is consolidated in a central reporting system and analysed against the operating profile of each site, so that consumption is judged against activity rather than in absolute terms. Emissions are calculated under the GHG Protocol approach using project specific emission factors of the relevant energy sources.

Four intervention areas were prioritised from that analysis. Lighting was addressed through automation based on the digital addressable lighting interface standard, together with light meter integration so that artificial lighting responds to daylight rather than running at a fixed level. Heating, ventilation, air conditioning and chiller systems were optimised against actual load. Heating systems were revised. Solar-supported hot water was brought into service where hot water demand justified it.

Investment prioritisation is part of the model rather than a separate budgeting exercise. Measures requiring low investment are implemented quickly, and measures requiring higher investment are ranked by payback period, carbon reduction potential and operational effect, which keeps financial and environmental objectives in the same decision.

Verification closes the loop. Consumption before and after implementation is analysed by the same method, on monthly and annual cycles rather than only at project completion, and proven measures are standardised so they can be applied at other operation centres to the same specification.

Figure 1: Annual energy consumption at the operation centres before and after implementation, over the 2024–2025 measurement period: electricity down 828,705 kWh, or 10.0 per cent, and natural gas down 797,107 kWh, or 8.8 per cent.

Figure 2: The four intervention areas inside an operation centre: lighting automation with light meter integration, heating, ventilation and air conditioning optimisation, heating system revision, and solar-supported hot water.


Impact

Sustainability Impact

Climate

The initiative targets Scope 1 emissions from natural gas burned for heating and hot water at the operation centres, and Scope 2 emissions from purchased electricity used for lighting, cooling and building services. Emissions are calculated under the GHG Protocol approach using the emission factors of the relevant energy sources, with 2024 as the base year and pre-implementation and post-implementation consumption analysed by the same method.

Over the 2024-2025 period, annual electricity consumption was reduced by 10 per cent, from 8,317,528 kWh to 7,488,823 kWh, and natural gas consumption was reduced by 9 per cent, from 9,011,548 kWh to 8,214,441 kWh.

Those reductions prevented a total of 509 tonnes of CO2e from being generated.

Measurement is not limited to project completion. Consumption is compared on monthly and annual cycles, so a measure whose performance decays becomes visible instead of being assumed to hold, and the same data identifies the next improvement opportunity.

The results support the company's climate commitments announced in 2022, which target net zero for emissions from its own operations by 2040 and for value chain emissions by 2050.

The consolidated programme was established in 2026 by bringing together energy efficiency initiatives that had already been implemented across Trendyol's operation centres. The reported results are based on measured operational performance during the 2024–2025 period and cover 5 operation centres in Türkiye. Greenhouse gas emissions were calculated in accordance with the GHG Protocol using DEFRA 2025 emission factors for natural gas combustion and the applicable electricity emission factors for Türkiye.

Nature

Solar-supported hot water displaces natural gas combustion at the point of use, which removes local combustion emissions as well as the associated fuel consumption.

Lower electricity demand reduces the generation required to serve these sites, and with it the water and fuel consumed upstream in generation.

Lighting automation reduces artificial light output when daylight is sufficient, which lowers light emission from large facilities in addition to reducing consumption.

Business Impact

Benefits

The direct benefit is a lower energy bill. Electricity consumption fell by 10 per cent and natural gas by 9 per cent on the volumes reported, and because the measures are physical and standardised, the saving persists rather than depending on behaviour.

Continuous monitoring produces a second benefit that is operational rather than financial. Consumption anomalies indicate equipment faults, so heating, ventilation, air conditioning and chiller problems are detected from the energy data before they affect working conditions in the facility.

Energy performance has become one of the operating indicators of the operation centres rather than a technical matter for facilities teams alone, which means energy cost, operational efficiency and carbon reduction are weighed in the same management decision.

Standardising proven measures reduces the cost of applying them at the next site, because specification, supplier selection and verification method are already defined, which shortens implementation time as the programme extends across the network.

Energy cost savings are tracked internally in Turkish lira as a key performance indicator. However, these figures are commercially sensitive and are therefore not publicly disclosed.

Costs

The investment covers lighting automation and light meter integration, optimisation of heating, ventilation, air conditioning and chiller systems, revision of heating systems, and solar-supported hot water installations, together with the metering and building management data infrastructure that makes the results verifiable.

The measurement layer carries its own continuing cost: meters, building management system integration, central reporting and the analytical effort to compare consumption periods on a consistent basis.

Measures requiring low investment are implemented quickly, while higher-investment measures are prioritised by payback period, carbon reduction potential and operational effect, which spreads capital demand across annual investment plans and operational improvement budgets rather than requiring a single allocation.

Savings depend on the operating profile of each site. A facility with different shift patterns, floor area or climate exposure will not reproduce the same percentages, so each site needs its own analysis before investment is committed.

The residual dependency is verification discipline. Without consistent before-and-after analysis the savings cannot be defended, and the case for the next investment weakens accordingly.

The programme comprises multiple energy efficiency initiatives implemented through annual operational improvement plans rather than a single investment project. Accordingly, no programme-level investment amount is tracked. Investment requirements and realised payback periods are assessed individually for each initiative through the company's standard capital allocation and operational budgeting processes.

Impact Beyond Sustainability And Business

Co-benefits

Better controlled lighting and conditioning improve working conditions in large facilities, because systems respond to actual conditions rather than running at fixed settings.

The monitoring infrastructure has uses beyond energy. The same consumption data supports maintenance planning and equipment life management, since a rising consumption trend usually indicates a developing fault.

Suppliers involved in energy analysis, system optimisation and engineering design develop technical capability through the work, which they carry into other projects, and the shared learning strengthens the technical base available to the sector.

Because the method is not tied to a particular technology, it applies to warehouses, production facilities, offices and commercial buildings of different sizes, which makes it transferable well beyond logistics.

Potential side-effects

Automation increases dependence on control systems and on the data infrastructure behind them. A failed sensor or a mis-set schedule can raise consumption rather than lowering it, and the fault is invisible without the monitoring layer that detects it.

Efficiency gains are also exposed to growth. Absolute consumption can rise again as the operation expands even where intensity continues to improve, so energy intensity has to be reported alongside absolute figures to avoid overstating progress.

Measures optimised for one operating profile do not transfer unchanged. Applying a specification proven at one centre to a site with different shift patterns or climate exposure can produce a smaller saving than expected, which is why site-level analysis precedes each rollout.

There is also a limit to the approach. Efficiency reduces consumption but cannot remove the remaining emissions, so the operations net zero target for 2040 depends on energy supply decisions beyond this initiative.


Implementation

Typical Business Profile

The model suits companies operating a network of large facilities with continuous energy demand, including logistics and fulfilment centres, warehouses, production sites, offices and commercial buildings, where consumption is significant and facilities are managed centrally.

It is most relevant for operators running several sites of comparable design, because the value comes from standardising a proven measure and transferring it, and for businesses whose operational growth is raising energy consumption faster than efficiency is improving it.

Delivery engages the sustainability function, operations management and facility management teams, working with suppliers that provide energy analysis, system optimisation and engineering design.

Approach

  1. Instrument consumption before selecting measures: Draw electricity and natural gas data from building management systems, meter readings and facility performance records into a central reporting system, so improvement opportunities are chosen from data rather than from assumption.

  2. Fix a base year and a comparison method: Use a defined base year, in this case 2024, and analyse pre-implementation and post-implementation consumption by the same method, so every project result is comparable and defensible.

  3. Identify the highest-consumption areas first: Analyse where energy is actually consumed across lighting, heating, ventilation, air conditioning and hot water, and set intervention priorities from that profile rather than from the availability of technology.

  4. Automate lighting against daylight: Implement lighting automation based on the digital addressable lighting interface standard and integrate light meters, so artificial lighting responds to daylight instead of running at a fixed level.

  5. Optimise conditioning systems against real load: Tune heating, ventilation, air conditioning and chiller operation to the actual load profile of the facility, and revise heating systems where the existing configuration no longer matches the space.

  6. Add renewable supply where demand justifies it: Bring solar-supported hot water into service at sites with sufficient hot water demand, to displace natural gas at the point of use.

  7. Prioritise investment by payback and carbon: Implement low-investment measures immediately, and rank higher-investment measures by payback period, carbon reduction potential and operational effect, so financial and climate objectives are decided together.

  8. Verify monthly and standardise what works: Compare consumption on monthly and annual cycles rather than only at project completion, calculate avoided emissions under the GHG Protocol approach, and convert proven measures into standard specifications for other operation centres.

Stakeholders Involved

  • Project leads: The programme is one of the operational applications of the net zero commitments the company announced in 2022, and it is reviewed regularly by senior management, with operational performance, cost efficiency and carbon reduction indicators integrated into strategic decision-making. That review cycle is what secures the annual investment plans and operational improvement budgets on which continuation depends.

  • Company functions: The sustainability and operations teams run the programme jointly, managing energy performance, investment priorities and implementation results together, so energy efficiency sits inside operations management rather than beside it. Logistics and facility teams define operational requirements, improvement areas and investment priorities from the site perspective, while the sustainability team calculates carbon reduction effects, tracks performance and manages reporting to international reporting standards.

  • Main providers: Suppliers specialising in energy efficiency contribute energy analysis, system optimisation and engineering solutions to project design. They work with the facility teams rather than delivering turnkey installations, so requirements from the operating floor shape the specification. Feedback from suppliers and field teams is used to identify new improvement opportunities and to refine measures already in service.

  • Other: Project decisions are taken jointly against energy saving potential, operational suitability, payback period and carbon reduction effect, so no single function decides alone. Results are shared with the teams involved, and successful applications are standardised and transferred to other operation centres, which is what turns supplier and site learning into network-wide practice.

Key Parameters To Consider

Performance is tracked through five key performance indicators: total electricity saving in kWh, total natural gas saving in kWh, greenhouse gas emissions avoided in tCO2e, energy cost saving in Turkish lira, and the improvement in energy intensity.

The method depends on data rather than on a specific technology, which is why it transfers across facility types, but each site needs its own consumption analysis because operating profile, floor area and climate exposure determine the achievable saving.

Measurement runs on monthly and annual cycles, so the programme is a continuous improvement structure rather than a project with a completion date, and results feed investment prioritisation for the following period.

Financial sustainability and operational rollout are managed together: low-investment measures spread quickly and fund credibility for the higher-investment measures that follow.

Implementation And Operations Tips

Instrument first and invest second. Where consumption is not measured against operating profile, investment goes to the most visible system rather than the largest consumer.

Compare against activity, not only against last year. Absolute consumption moves with order volume, so energy intensity is the indicator that shows whether efficiency is genuinely improving.

Keep measuring after the project closes. Automation settings drift and equipment degrades, and monthly comparison is what distinguishes a saving that holds from one that quietly disappears.

Standardise the specification, not just the outcome. Writing up the proven configuration, the supplier requirement and the verification method is what makes the second and third installation cheaper than the first.

Put energy performance into operational indicators rather than technical reports. Once site management is accountable for consumption, low-cost operating changes surface without needing an investment case.